Phase II photovoltaic successfully achieved grid-connected power generation
On June 4, 2024, the Phase II photovoltaic power generation project with an installed load of nearly 300 kW passed the acceptance inspection by the power bureau and successfully achieved grid-connected power generation. As of June 19, it had generated 12.68 MWh of electricity, bringing substantial economic and environmental benefits to the company.
![]()
Against the backdrop of the country’s promotion of energy structure transformation and enhanced environmental protection awareness, the company actively practices ESG concepts, fully participates in the national “dual carbon” goal plan, and is committed to special work such as energy conservation, emission reduction and green energy transformation, achieving good results. Since 2022, after a professional team conducted a structural feasibility analysis on the company’s existing factories available for photovoltaic power generation, the company decided to utilize the existing factory roof resources to develop solar photovoltaic power generation projects.
![]()
In early 2023, the design of the Phase I distributed photovoltaic power generation project was completed, and it was successfully installed on the roofs of the company’s office building and Class C warehouse. The total installed capacity of the project reached 252.525 kW, using high-efficiency monocrystalline silicon photovoltaic modules, each of which can output 550 W of power under standard test conditions. The project passed the power grid acceptance in June 2023 and successfully connected to the grid, which not only met the company’s own electricity demand, but also provided clean energy to the power grid, further optimizing the energy structure.
![]()
Up to now, the Phase I photovoltaic project has accumulated 284.127 MWh of power generation, reduced CO₂ emissions by 283.28 tons, saved 113.65 tons of standard coal, equivalent to the environmental benefit brought by planting 157.41 green plants.
To further expand the scale of photovoltaic power generation, in early 2024, after the completion of the acceptance of the Phase II “16kt/a Addition-Cure Liquid Silicone Rubber (LSR)” project construction project, the design of the “Phase II Roof Distributed Photovoltaic” project was immediately completed. 580 high-efficiency monocrystalline photovoltaic modules of 590 W were installed in the Phase II Class C workshop and Class C warehouse, with an installed capacity of 292.4 kW. The project was quickly declared and started construction, and completed the grid connection with the national power grid on June 4, 2024.
![]()
Senri’s photovoltaic power generation project is an important part of the company’s green development strategy, demonstrating the company’s firm commitment to environmental protection and sustainable development. With the advancement of the Phase II project, we look forward to the company achieving greater achievements in the field of green energy and contributing more to the realization of the carbon neutrality goal.